F08 Installation & Programming Manual
Document No: LT0082
Placing into Operation
3.4
COMMISSIONING CHECKLIST
The commissioning of an F08 FIP is the most important phase of any contract.
If any problems are not corrected in this stage, experience shows that even the simplest of
mistakes can cause major problems over a long period of time.
The following procedure should be regarded as the minimum requirements for a
commissioning check.
Please complete this checklist carefully. Some major points to be noted are:
1.
Ensure that the F08 FIP is correctly programmed to meet statutory requirements and
the Customer's specifications.
2.
Ensure the INSTALLATION meets the standards defined by AS1670.1 and any other
local standards.
3.
Ensure that the "AS INSTALLED" drawing represents the TRUE site installation,
complete with;
(a)
Detector location and types.
(b)
F08 FIP Programmed Configuration.
4.
Ensure that a copy of the "AS INSTALLED" drawing is included inside the panel for
maintenance purposes.
5.
Ensure that a copy of the "F08 OPERATOR'S MANUAL" is included inside the panel
and the system detail pages are completed.
6.
Ensure that interface devices are connected to the "AUXILIARY OUTPUTS" if these
outputs are used externally.
7.
Ensure that only APPROVED brigade interfacing devices are connected to the
brigade relays; "STANDBY", "FAULT", "ISOLATE", and "ALARM" (FIRE).
-
Approved interfaces include:
(a) Randata
Deltec
(b) Minimux
Deltec
(c) Torrens
Transponder
via Transponder Interface Adapter - TIA001
(d)
Line Isolating Unit - LIU001
(e)
MFB - Alarm Interface Unit.
(f)
Tyco Fire Monitoring - Centaur.
8.
Ensure that all ENABLED ZONES, ANCILLARY RELAY and ALARM BELLS can be
isolated.
9.
Ensure batteries are charged and that a battery test passes. Turn off the mains
switch and check the system operates off the batteries.
Page 3-6
24 March 2006
Issue 3.04