5.4.3 Mortar-based installation with partial mortaring
Fig. 32: Mortar-based installation into a solid wall, with partial mortaring
1
FKRS-EU
2.1
Mortar
3.1
Solid wall
4.1
Solid ceiling slab
6.4
Mineral wool,
≥
1000 °C,
≥
140 kg/m³
–
Up to EI 120 S
Additional requirements: mortar-based installation into solid walls with partial mortaring
Solid wall
40 – 50 mm distance to load-bearing structural elements
Distance between two FKRS-EU in one installation opening 40 – 225 mm
1.
The difficult-to-access installation gap between the FKRS-EU and the wall / ceiling slab must be completely
filled in the wall area.
2.
Completely close off the remaining gaps »s« (on 2 or 3 sides) with mortar.
Installation
Solid walls > Mortar-based installation with partial mortari...
Fire damper Type FKRS-EU
44
Summary of Contents for FKRS-EU
Page 176: ...Fire damper Type FKRS EU 176...