Q9 ASD Installation and Operation Manual
25
Startup and Test
Before turning on the ASD ensure that:
• The enclosure door is closed or reattached, and secure.
• R/L1, S/L2, and T/L3 are connected to the 3-phase input power.
• U/T1, V/T2, and W/T3 are connected to the motor.
• The 3-phase input voltage is within the specified tolerance.
• There are no shorts and all grounds are secure.
• All personnel are at a safe distance away from the motor and/or the motor-driven equipment.