![Tektronix TDS 500C Performance Verification Manual Download Page 46](http://html1.mh-extra.com/html/tektronix/tds-500c/tds-500c_performance-verification-manual_1079136046.webp)
Performance Tests
1–30
TDS 500C, TDS 600B & TDS 700C Performance Verification and Specifications
1. Install the test hookup and preset the instrument controls:
a. Hook up the test-signal source:
H
Set the output of a DC calibration generator to 0 volts.
H
Connect the output of a DC calibration generator through a
dual-banana connector followed by a 50
W
precision coaxial cable to
one side of a BNC T connector. See Figure 1–5.
H
Connect the Sense output of the generator through a second
dual-banana connector followed by a 50
W
precision coaxial cable to
the other side of the BNC T connector. Now connect the BNC T
connector to CH 1. See Figure 1–5.
DC Calibrator
50
coaxial cables
Dual banana to
BNC adapters
BNC T
connector
Digitizing Oscilloscope
Output
Sense
Figure 1–5: Initial test hookup
b. Initialize the oscilloscope:
H
Press save/recall SETUP.
H
Press the main-menu button Recall Factory Setup.
H
Press the side-menu button OK Confirm Factory Init.
c.
Modify the default settings:
H
Press SHIFT; then press ACQUIRE MENU.
H
Press the main-menu button Mode; then press the side-menu button
Average 16.
2. Confirm input channels are within limits for DC accuracy at maximum offset
and position: Do the following substeps — test CH 1 first, skipping substep
2a since CH 1 is already selected from step 1.
Summary of Contents for TDS 500C
Page 4: ......
Page 15: ...Performance Verification Procedures ...
Page 16: ......
Page 115: ...Specifications ...
Page 116: ......
Page 132: ...Nominal Traits 2 16 TDS 500C TDS 600B TDS 700C Performance Verification and Specifications ...
Page 147: ......
Page 148: ......