4 Getting Started
4.7 Commissioning
32
SICAM I/O Unit, 7XV5673, Device Manual
E50417-H1040-C484-A3, Edition 05.2012
4.7
Commissioning
4.7.1
Initial and Current Commissioning
After you have inserted the battery, assembled the device and connected the supply voltage lines, you can start
the device for the first time. Proceed as follows:
✧
Check that the operational data match the rated data on the label and the technical data of the device (see
chapter 11.1). This applies in particular to the supply voltage.
✧
On the side of the terminal of the device, connect the transmission lines to the terminal blocks N and P.
✧
Connect the lines, for example for systems control, on connection J (RS485 or serial FO interface) on the
side of the terminals of the device.
✧
On the top side of the device, connect the network cable to the PC at the RJ45 socket Z (Ethernet).
✧
Close the door of the control cabinet to prevent touching live parts accidentally.
✧
Switch on the connected peripheral devices (for example PC).
✧
Switch on the supply voltage of the device.
DANGER
Hazard posed by high contact voltage.
Non-observance leads to death or serious injury.
✧
Only trained personnel (see Preface), who is familiar with the safety requirements and precautions and
observes them can carry out the work.
✧
If there is any dangerous voltage present, work may never be carried out.
✧
De-energize the device.
✧
For disconnecting the voltage and current, a suitable separator is connected in series to de-energize the
device!
✧
Secure the supply voltage with an approved (UL/IEC) fuse: 1.6 A, type C.
✧
If a melting fuse is used, a suitable approved (UL/IEC) fuse holder has to be used.
NOTE
Only wire the terminals that are necessary for this purpose.
NOTE
The device does not have a power on/off switch. The supply voltage must be switched on or off directly at the
respective supply cable.
MAN_SICAM_IO-Unit_7XV5673_US.book Page 32 Thursday, May 10, 2012 10:59 AM