Chapter 2 Installing the P1000 Library
Unpacking the P1000
ATL P1000 Series User’s Guide
17
Unpacking the P1000
2
This section explains how to receive and unpack the P1000.
Note: If you have already unpacked the library following the procedures in
the ATL P1000 Series Unpacking Instructions, skip ahead to “Preparing
and Inserting Tape Cartridges” on page 30.
This procedure consists of the following steps:
•
receiving the library from the shipper
•
uncrating the library
•
checking the contents of the shipping carton and accessories tray
•
installing the slide assembly in the rack (rack-mount library only)
•
removing the library from the pallet
•
removing the internal packing materials from the library
Note: Before performing the procedures in this section, verify that the
installation site meets the requirements listed in “Site Requirements”
on page 14.
Unloading Space
Requirements
2
Before uncrating the library, verify that you have sufficient space. For
the stand-alone unit, allow a minimum of six feet in front of the ramp
side of the pallet (see figure 12 on page 18).
Note: Unpack the library as close to the installation site as possible.
Summary of Contents for P1000 Series
Page 1: ...ATL P1000 Series Tape Library User s Guide 6221101 03 Ver 3 Rel 0...
Page 8: ...Contents viii ATL P1000 Series User s Guide...
Page 12: ...Tables xii ATL P1000 Series User s Guide...
Page 16: ...Preface xvi ATL P1000 Series User s Guide...
Page 72: ...Chapter 3 Basic Operations Performing Manual Operations 56 ATL P1000 Series User s Guide...
Page 88: ...Chapter 4 Operator Commands Unloading the Load Port 72 ATL P1000 Series User s Guide...
Page 112: ...Appendix A Specifications 96 ATL P1000 Series User s Guide...