Assembly and commissioning
Version 1.1.2 dated 2019-05-07
Page 230
Translation of the original instructions
F80 | F105
GB
F
80_F105
_GB
_3.
fm
OPTIMUM
M A S C H I N E N - G E R M A N Y
®
3
Assembly and commissioning
INFORMATION
The CNC-machine is delivered pre-assembled. It is delivered in a transport box.
3.1
Scope of delivery
Compare the delivery volume with the attached packing list.
Check the status of the CNC-machine immediately upon receipt and claim possible damages at
the last carrier also if the packing is not being damaged. In order to ensure claims towards the
freight carrier we recommend you to leave the machines, devices and packing material for the
time being in the status at which you have determined the damage or to take photos of this
status. We would like to ask you to inform us about any other claims within six days upon
receipt of the delivery.
Check if all parts are firmly seated.
3.2
Transport
WARNING!
Severe or fatal injuries may occur if the machine or parts of the machine tumble or fall
down from the forklift truck or from the transport vehicle. Follow the instructions and
information on the transport case:
WARNING!
Use of unstable lifting equipment and load-suspension gears that break under load can
cause very serious injury or even death.
Check that the lifting and load suspension gear has sufficient load capacity and that it is
in perfect condition.
Observe the accident prevention regulations.
Fasten the loads properly.
Never walk under suspended loads!
Check the substructure. The substructure has to bear the load.
Dismount the side parts of the wooden box.
The CNC-machine is lifted and transported with an appropriate handling device to the
installation place by means of a fork-lift truck.
Disassemble the clamping bolts which are used to fix the machine on the pallet.
Centres of gravity
Load suspension point
(Marking of positions for the load suspension
point)
Prescribed transportation position
(Marking of the top surface)
Means of transport to be used
Weights