INSERT HYDRAULIC REQUIREMENTS
Refer to “Spreader Hydraulic Requirements” for specifications required for insert installation.
SPREADER PREPARATION
WARNING
Use only lifting devices that meet or exceed OSHA standard 1910.184. Never exceed work
load limits or lift equipment over people. Empty spreader before lifting. Loads may shift
or fall if improperly supported, causing injury.
1.
Remove the Inverted “V”, Hillside Divider and side boards
from the spreader, if so equipped, and set hardware aside.
Replace chain shield hardware from Hillside Divider and
torque to spec.
2.
Figure 1 - Disconnect feedgate hydraulic hoses (A)
.
B
AA
Figure 1
3.
Figure 2 - Disconnect Endgate harness at rear electrical
bulkhead. Uncap all necessary receptacles.
BIN 3
BIN 4
BIN 2
BIN 1
BIN 3
BIN 4
BIN 2
BIN 1
Figure 2
Recommended sequence of installation is:
1.
Spreader preparation.
2.
Insert preparation.
3.
Mounting of insert.
4.
Connecting hydraulic hoses.
5.
Installation of hillside divider and conveyor cover.
6.
Checking installation.
7.
Checking for leaks and proper functioning.