(1) The machine always automatically decelerates each time the positioning is
completed. Acceleration is then carried out after the QD75 command speed
reaches 0 to carry out the next positioning data operation. If a dwell time is
designated, the acceleration is carried out after the designated time elapses.
(2) In operation by continuous positioning control (operation pattern "01"), the
next positioning No. is automatically executed. Always set operation pattern
"00" in the last positioning data to complete the positioning.
If the operation pattern is set to positioning continue ("01" or "11"), the
operation will continue until operation pattern "00" is found.
If the operation pattern "00" cannot be found, the operation may be carried
out until the positioning data No. 600. If the operation pattern of the
positioning data No. 600 is not completed, the operation will be started again
from the positioning data No. 1.
Time
OFF
ON
OFF
ON
OFF
ON
OFF
Positioning continue (01)
Address (+) direction
Address (-) direction
Positioning
complete (00)
Dwell
time
ON
Positioning continue (01)
Start complete signal
BUSY signal
Positioning complete signal
Positioning start signal
[Y10, Y11, Y12, Y13]
[X10, X11, X12, X13]
[XC, XD, XE, XF]
[X14, X15, X16, X17]
Dwell time
not designated
Fig. 9.2 Operation during continuous positioning control
Summary of Contents for D75D4
Page 2: ......
Page 22: ...A 20 MEMO ...
Page 24: ...MEMO ...
Page 41: ...1 17 MELSEC Q 1 PRODUCT OUTLINE MEMO ...
Page 48: ...1 24 MELSEC Q 1 PRODUCT OUTLINE MEMO ...
Page 58: ...2 10 MELSEC Q 2 SYSTEM CONFIGURATION MEMO ...
Page 65: ...3 7 MELSEC Q 3 SPECIFICATIONS AND FUNCTIONS ...
Page 139: ...5 35 MELSEC Q 5 DATA USED FOR POSITIONING CONTROL MEMO ...
Page 238: ...5 134 MELSEC Q 5 DATA USED FOR POSITIONING CONTROL MEMO ...
Page 251: ...6 13 MELSEC Q 6 SEQUENCE PROGRAM USED FOR POSITIONING CONTROL ...
Page 254: ...6 16 MELSEC Q 6 SEQUENCE PROGRAM USED FOR POSITIONING CONTROL ...
Page 255: ...6 17 MELSEC Q 6 SEQUENCE PROGRAM USED FOR POSITIONING CONTROL ...
Page 256: ...6 18 MELSEC Q 6 SEQUENCE PROGRAM USED FOR POSITIONING CONTROL ...
Page 259: ...6 21 MELSEC Q 6 SEQUENCE PROGRAM USED FOR POSITIONING CONTROL ...
Page 260: ...6 22 MELSEC Q 6 SEQUENCE PROGRAM USED FOR POSITIONING CONTROL ...
Page 292: ...7 8 MELSEC Q 7 MEMORY CONFIGURATION AND DATA PROCESS ...
Page 294: ...7 10 MELSEC Q 7 MEMORY CONFIGURATION AND DATA PROCESS ...
Page 298: ...MEMO ...
Page 462: ...9 140 MELSEC Q 9 MAJOR POSITIONING CONTROL MEMO ...
Page 490: ...10 28 MELSEC Q 10 HIGH LEVEL POSITIONING CONTROL MEMO ...
Page 524: ...11 34 MELSEC Q 11 MANUAL CONTROL Creating the program ...
Page 666: ...14 24 MELSEC Q 14 DEDICATED INSTRUCTIONS MEMO ...
Page 675: ...15 9 MELSEC Q 15 TROUBLESHOOTING MEMO ...
Page 716: ...15 50 MELSEC Q 15 TROUBLESHOOTING MEMO ...
Page 725: ...Appendix 9 MELSEC Q APPENDICES MEMO ...
Page 878: ...Appendix 162 MELSEC Q APPENDICES 6 QD75D4N 90 23 27 4 12 98 4 46 Unit mm ...
Page 879: ...Appendix 163 MELSEC Q APPENDICES 7 QD75P1 QD75P2 QD75P4 27 4 23 98 90 4 46 unit mm ...
Page 880: ...Appendix 164 MELSEC Q APPENDICES 8 QD75D1 QD75D2 QD75D4 27 4 23 90 12 98 4 46 unit mm ...
Page 893: ...WARRANTY ...
Page 895: ......