2-22
A-61593 September 2007
The Task table
Each row in the Task table corresponds to a run. A column can be
sorted in ascending or descending order by clicking on the table
header.
Task table for Convert
and Transfer
The Task table below represents what the Task table looks like when
you are using Convert or Transfer and is followed by column
descriptions.
Task name
— unique name of the run.
Action
— indicates the action being taken by the run depending on the
module in use.
•
Convert
: converts output format
•
Transfer
: transfers the files to the output destination folder
•
Split:
Secondary run
Status
— provides the current state of the run.
The number of tasks
processed at one time depends on the system configuration. In batch
mode, the task is put into the P2 queue; in manual mode, the task is put
into the P1 queue.
Default (no arrow)
Ascending order (up arrow)
Descending order (down arrow)
Status
Description
open
a run is in the queue and waiting to be
processed
processing
a run is currently in process
closed
a run was successfully completed
failed
a run could not be processed