7-36 Keysight N5290/1A Service Guide
Repair and Replacement Procedures
Post-Repair Procedures
7-
Post-Repair Procedures
After the replacement of an assembly, you must perform the service
procedures in the order listed in
.
Procedures referenced in this table are located in
unless specified otherwise.
STOP!
Before returning the repaired instrument to the customer, it is
critical to ensure the product is safe for use. Before powering on the
instrument, verify there is ground continuity between the ground
terminal on the AC Inlet and the metal frame of the product. It is
also critical to perform a voltage test on the outer surfaces of the
product to confirm the instrument does not present an electric
shock hazard.
IMPORTANT!
Before you begin any testing on a System or instrument,
always inspect the connectors on the instrument, the calibration kit,
cables and adapters.
to review where the
calibration stickers should be placed on the N5292A.
Table 7-2
Related Service Procedures
Replaced Assembly
Adjustments
and Other Procedures
Verification, Performance,
and Other Tests and Procedures
N5292A Test Set
Front panel and subpanel
assemblies
No adjustment needed
Check for proper operation.
A1 power supply assembly
No adjustment needed
Millimeter head heater DAC
Millimeter power supplies verification
A2 LOPA assembly
No adjustment needed
’LO Verify all ports (with corrections)’
A3 Phase compensation PCA
No adjustment needed
’LO Verify all ports (with corrections)’
A4 LODA assembly
No adjustment needed
’LO Verify all ports (with corrections)’
Summary of Contents for N5222B
Page 3: ...3 ...
Page 4: ...4 ...
Page 10: ...6 Keysight N5292A User s and Service Guide Contents ...
Page 28: ...1 18 Keysight N5290 1A Service Guide Safety and Regulatory Information Site Preparation 1 ...
Page 86: ...3 50 Keysight N5290 1A Service Guide System Tests and Adjustments Adjustments 3 ...
Page 128: ...5 10 Keysight N5290 1A Service Guide Theory of Operation Theory of Operation 5 ...
Page 225: ...Installation Note Xxxxx xxxxx 3 ...