4 - 7
Port Relief for Boom Ram
1. Prepare the machine
a.
Put the operator lever into neutral, lower the gate lock
lever. Start the engine and place the machine on
level ground, lower and open the arm and set the
bucket on the ground.
b.
Stop the engine, and release hydraulic pressure.
(See
Releasing Tank Pressure
).
c.
Connect a 0-500 bar (0-7000 lb/in
2
) pressure gauge
and adaptor to port P2 on the hydraulic pump.
2.
Refer to the previous section "Temporary setting of main
relief pressure" and complete step 2.
3. Pressure Adjustment
a.
Start the engine and lower the gate lock lever, run
the
engine at maximum no-load speed and in the
S
mode.
b.
Position the boom lever in the raised position and
maintain.
c.
Check the gauge for the set pressure of 377 bar ±
14.4 bar (5546 ± 213 lb/in
2
). If it is outside the limits,
adjust the port relief valve
A
by loosening the lock nut
B
and always coming up to the correct set pressure
by first unscrewing, and then screwing in adjusting
screw
C
.
4.
Adjust the boom lowering port relief valve
D
, as above,
to the set pressure of 241 ± 14.4 bar (3555 ± 213 lb/in
2
)
by first positioning the boom lever in the lowered position
and maintaining it.
5.
If the boom cannot be lowered fully, the two ARV's can
be exchanged so that the ARV of the boom lowering can
be adjusted in the boom raising position (boom lever in
raised position) and then replaced.
6. Adjust the main relief Pressure
See previous section "Temporary setting of main relief
pressure", item 3.
7.
Stop the engine and release the hydraulic pressure,
(see
Releasing Tank Pressure
)
, remove the pressure gauge
and adaptor.
Section E
Hydraulics
9803/6400
Section E
4 - 7
Issue 1
Pressure Testing
D
A
C
B
Summary of Contents for JS 200 Series
Page 57: ...9 1 Section 3 Routine Maintenance 9803 6400 Section 3 9 1 Issue 2 Component Location Diagram...
Page 113: ......
Page 137: ...5 3 Section C Electrics 9803 6400 Section C 5 3 Issue 2 Pump Control FLOW CHART...
Page 201: ...10 7 Section C Electrics 9803 6400 Section C 10 7 Issue 1 CAPs II Diagnostic system K C...
Page 215: ...Section E Section E Hydraulics 9803 6400 Issue 2 3 2 3 2 Schematics...
Page 217: ...Section E Section E 9803 6400 Issue 2 3 3 3 3 Hydraulics Schematics...
Page 218: ...3 5 Section E Hydraulics 9803 6400 Section E 3 5 Issue 1 Schematics Shuttle Block JS200 JS240...
Page 232: ...10 1 Section E Hydraulics 9803 6400 Section E 10 1 Issue 1 Hydraulic Pump JS200 JS240...
Page 233: ...10 2 Section E Hydraulics 9803 6400 Section E 10 2 Issue 1 Hydraulic Pump JS200 JS240...
Page 234: ...10 3 Section E Hydraulics 9803 6400 Section E 10 3 Issue 1 Hydraulic Pump JS200 JS240...
Page 263: ...30 2 Section E Hydraulics 9803 6400 Section E 30 2 Issue 1 Control Valve JS200 JS240...
Page 264: ...30 3 Section E Hydraulics 9803 6400 Section E 30 3 Issue 1 Control Valve JS200 JS240...
Page 265: ...30 4 Section E Hydraulics 9803 6400 Section E 30 4 Issue 1 Control Valve JS200 JS240...
Page 266: ...30 5 Section E Hydraulics 9803 6400 Section E 30 5 Issue 1 Control Valve JS200 JS240...
Page 267: ...30 6 Section E Hydraulics 9803 6400 Section E 30 6 Issue 1 Control Valve JS200 JS240...
Page 268: ...30 7 Section E Hydraulics 9803 6400 Section E 30 7 Issue 1 Control Valve JS200 JS240...
Page 327: ...51 12 Section E Hydraulics 9803 6400 Section E 51 12 Issue 1 Solenoid Valve 8 spool...
Page 328: ...55 1 Schematic Section E Hydraulics 9803 6400 Section E 55 1 Issue 1 Shuttle Valve...
Page 330: ...55 3 Schematic Section E Hydraulics 9803 6400 Section E 55 3 Issue 1 Cushion Valves...
Page 481: ...7 15 Section F Transmission 9803 6400 Section F 7 15 Issue 2 Motor...
Page 482: ...7 16 Section F Transmission 9803 6400 Section F 7 16 Issue 1 Motor...