Installation / Assembly
T-Rack
®
3.0 Series
– Assembly Instructions 1.1(2019-03) E inge
Page 63 of 84
© inge GmbH
Step
Activity
Figure
1
Mount the bottom frame of the second sub-unit
Mount the bottom frame as described in section:
2
Adjust the bottom frame to the existing sub-unit
Number of persons: 2
a)
Position the frame at the correct location according to the
system layout.
b)
Place the spirit level on the channel section (DIN 1026) that
is closest to the existing sub-unit.
c)
Loosen the nuts on both connection-side frame feet of the
new bottom frame.
d)
Move the new bottom frame to the height of the existing
sub-unit using the spirit level.
e)
Secure the two connection-side frame feet of the new
bottom frame by hand-tightening the nuts.
f)
Align the new bottom frame as described in section:
Positioning and aligning the Bottom Frame
3
Mount the new sub-unit
Mount the modules and the filtrate headers as described in
sections:
Tightly screwing together the Channel Sections (DIN 1026)