![Huawei UPS5000-S-600 User Manual Download Page 81](http://html.mh-extra.com/html/huawei/ups5000-s-600/ups5000-s-600_user-manual_170106081.webp)
UPS5000-S-600 kVA
User Manual (Three-phase, Three-wire)
3 Installation
Issue 05 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
73
Figure 3-28
Connecting cables
(1) Mains input circuit breaker
(2) Shunt release
(3) Bypass input circuit breaker
----End
3.2.4 UPS Cable Connection Reference
Context
Keep away from cabinets when preparing cables to prevent cable scraps from entering the
cabinets. Cable scraps may cause ignition during power-on and result in personal injury
and device damage.
After installing cables, clean the cabinet top, bottom, copper bar wiring positions, and
other positions. Ensure that there is no dust or scraps inside and around cabinets.
Prepare terminals onsite. The length of the copper wire should be the same as that of the
part of the terminal that covers the conductor.
Procedure
Step 1
Route a cable into the cabinet and bind it to a nearby beam.