When the holes have been drilled insert Cleco‟s / skinpins to hold in
position.
Then move to drilling and fixing the fairing front sides to the TU6. Just
make one hole each side and secure with Cleco‟s / skinpins.
The upper and lower seams have the positions marked for hole drilling with
small dots in the moulding. Start nearest the finpost. Drill, secure with
cleco/skinpins and move forwards.
Then move to the underside starting at the rear and again working
forwards.
Figure 122
fuselage fairing seams held togther with Cleco’s, bracing angles
g) When all is drilled and verified drill and rivet the remaining positions on the
finpost (fig 120). Use 5 white 4mm aluminium rivets.
h) Then fix the top and bottom fairing seams using the white 4x10mm plastic
screws and plastic self locking nuts. Use a 4x16mm stainless steel screw and
nyoc nut for the frontmost fixings top and bottom.
Make up some „creeper boards‟ (from the packing box is ideal) to put
on the lower longerons to gain access to the inside beyond what you
can easily reach.
i) Fit the two bracing angles shown in figure 122 above. These are there to
support / stiffen the glassfibre upper and lower surface
Make thes up from some 1mm thick aluminium, bent into an L shape.
Drill the horizontal tubes of the central frame 4mm holes in the centre to
fix them. Fix them to the nearest bolts in the fairing Change4 thse to
4mm bolts. Drill to fit to the central brace (4mm bolts) so that no
pressure is put on the glassfibre pushing or pulling.
Summary of Contents for Nynja Build
Page 1: ...1 Nynja Build manual Version 1 0...
Page 2: ...2 Figure 1 tube numbering scheme...
Page 3: ...3 Figure 2 Basic frame Skyranger...
Page 4: ...4 Figure 3 uncovered Skyranger frame...
Page 5: ...5 Figure 4 Uncovered Nynja frame Figure 5 Nynja fuselage with rear fairings removed...
Page 6: ...6 Figure 6 Nynja fuselage with rear fairings removed rear view Figure 7 simply assemble thus...
Page 22: ...22 Figure 13 forward fuselage from front quarter Figure 14 Cabin upper rear corner...
Page 60: ...60 Figures 65 cable arrangement further overview...
Page 86: ...86 Figure 100 Nynja elevator joiner with integral control horn...
Page 113: ...113 Figure 135 front jury strut attachment Figure 136 rear jury strut attachment...
Page 183: ...183 Figure 231 heavy duty power wiring schematic Rotax 912...
Page 184: ...184 Figure 232 low current wiring schematic Rotax 912...
Page 185: ...185 Figure 233 instrument wiring schematic Rotax 912...
Page 200: ...200 Nynja Build manual 1 0 18 2 One Piece Door Figure 250 one piece door frame...
Page 256: ...256 Nynja Build manual 1 0...
Page 257: ...257 Nynja Build manual 1 0 27 2 Wire locking...
Page 258: ...258 Nynja Build manual 1 0...
Page 259: ...259 Nynja Build manual 1 0...
Page 260: ...260 Nynja Build manual 1 0...
Page 265: ...265 Nynja Build manual 1 0...