Commissioning steps for a conventional substation with
modbus TCP environment:
•
Parameter setting of the IEDs;
•
Ethernet installation;
•
TCP/IP settings for the IEDs; and
•
Wiring according to wiring scheme.
Commissioning steps for a substation with IEC 61850
environment:
1. Parameter setting of the IEDs
Ethernet installation
TCP/IP settings for the IEDs
2. IEC 61850 configuration (software wiring)
a) Exporting an ICD file from each device
b) Configuration of the substation
(generating a SCD file)
c) Transmit SCD file to each device.