SCWD-QS (12/16)
Page 37
Start-Up Process
1) System Leak Check
After all indoor and outdoor refrigerant bearing components of the system have been installed and
joints have been nitrogen brazed, pressurize the system prior to evacuation to leak test the system.
Do not exceed 150 psig when pressure testing the compressor unit and indoor system components.
Test for leaks with a sensitive electronic leak detector and bubble solution.
Repair leaks as appropriate prior to evacuation.
Evacuation and charging of the system is done through the compressor unit. All of the refrigerant
containing components in the compressor unit are illustrated in Figures 23 and 24.
The Start-up Process is illustrated in Figure 31.
CAUTION!
During the Evacuation and Initial Charging processes, be sure that ALL
power to the EarthLinked
®
System is OFF. This includes the
compressor unit, air handler and all other electrically powered system
components. Failure to do so will cause lockout on start-up.
Summary of Contents for SCWD-024-1C
Page 15: ...SCWD QS 12 16 Page 15 Figure 7 SCWD Compressor Unit Electrical Schematic Diagram 230 1 60...
Page 16: ...SCWD QS 12 16 Page 16 Figure 8 SCWD Compressor Unit Electrical Schematic Diagram 230 3 60...
Page 17: ...SCWD QS 12 16 Page 17 Figure 9 SCWD Hydronic Heating Cooling Water Heating Sytem Application...
Page 20: ...SCWD QS 12 16 Page 20 Figure 11 SureStart Mode of Operation...
Page 31: ...SCWD QS 12 16 Page 31 Figure 14 Disassembled Plug Connector...
Page 38: ...SCWD QS 12 16 Page 38 Figure 23 SCWD Internal Flow Schematic...
Page 39: ...SCWD QS 12 16 Page 39 Figure 24 SCWD Piping...
Page 41: ...SCWD QS 12 16 Page 41 Figure 25 Evacuation of SCWD System...
Page 43: ...SCWD QS 12 16 Page 43 Figure 26 Initial Charge of SCWD System...
Page 45: ...SCWD QS 12 16 Page 45 Figure 27 Final Charge of SCWD System...
Page 48: ...SCWD QS 12 16 Page 48 Figure 31 Start Up Process...