The compressor unit package contains a service valve kit and an adapter kit.
The two service
valves are to be installed on the earth loop vapor and liquid connections of the compressor
unit,
using the adapters to right-size to the proper earth loop line set.
Installation of the service valves will provide isolation of the earth loop system from the compressor
unit and provide easy access to the refrigerant system.
For the installation of system components requiring refrigeration connections, refer to Figure 5 for line
set sizes and the appropriate installation manual(s) following Figure 5.
EARTH LOOP LINE SETS
COMPRESSOR UNIT SIZE
LINE SET O.D., INCHES
LIQUID*
VAPOR*
2.0 Tons (-024)
3/8
5/8
2.5 Tons (-030)
3/8
3/4
3.0 Tons (-036)
1/2
3/4
3.5 Tons (-042)
1/2
3/4
4.0 Tons (-048)
1/2
7/8
5.0 Tons (-060)
1/2
7/8
*Liquid and Vapor lines must BOTH be insulated with Armaflex® or
equivalent with at least 1/2” wall thickness for the vertical portions of the
line set.
Figure 5. Line Set Sizes
Series SV Service Valve and AKS Adapter Kit
Series HCM Hybrid Cooling Module
Earth Loop Specification and Installation Manual
After installing and nitrogen brazing the HVAC system components and compressor unit service
valves, turn the Service Valves to
Full Open
and pressurize the refrigeration system to 150 psig with
dry nitrogen and a trace of refrigerant. Valve off the nitrogen Tank from the HVAC system
components and check joints with a sensitive Electronic Leak Detector and bubble solution to ensure
they are sealed. Repair any leaks and re-test as appropriate.
Summary of Contents for SCWD-024-1C
Page 15: ...SCWD QS 12 16 Page 15 Figure 7 SCWD Compressor Unit Electrical Schematic Diagram 230 1 60...
Page 16: ...SCWD QS 12 16 Page 16 Figure 8 SCWD Compressor Unit Electrical Schematic Diagram 230 3 60...
Page 17: ...SCWD QS 12 16 Page 17 Figure 9 SCWD Hydronic Heating Cooling Water Heating Sytem Application...
Page 20: ...SCWD QS 12 16 Page 20 Figure 11 SureStart Mode of Operation...
Page 31: ...SCWD QS 12 16 Page 31 Figure 14 Disassembled Plug Connector...
Page 38: ...SCWD QS 12 16 Page 38 Figure 23 SCWD Internal Flow Schematic...
Page 39: ...SCWD QS 12 16 Page 39 Figure 24 SCWD Piping...
Page 41: ...SCWD QS 12 16 Page 41 Figure 25 Evacuation of SCWD System...
Page 43: ...SCWD QS 12 16 Page 43 Figure 26 Initial Charge of SCWD System...
Page 45: ...SCWD QS 12 16 Page 45 Figure 27 Final Charge of SCWD System...
Page 48: ...SCWD QS 12 16 Page 48 Figure 31 Start Up Process...