Operation & Maintenance Manual
Section3-User Responsibility, Machine
Preparation, and Inspection
Dingli Machinery
3-2
necessary inspections have been completed successfully before placing the machine into
service. These procedures will aid in obtaining maximum service life and safe operation.
The following table covers the periodic machine inspections and maintenance recommended
by Dingli Machinery Co, Ltd. Consult local regulations for further requirements for aerial
work platforms. The frequency of inspections and maintenance must be increased as
necessary when the machine is used in a harsh or hostile environment, if the machine is used
with increased frequency, or if the machine is used in a severe manner.
Table 3-1.Inspection and Maintenance Table
Type
Frequency
Primary
Responsibility
Reference
Pre-Start
Inspection
Before using each day;
or whenever there’s an
Operator change.
User or
Operator
Operator and Safety Manual
Pre-Delivery
Inspection
Before each sale, lease,
or rental delivery.
Owner, Dealer,
or User
Operation and Maintenance
Manual and applicable Dingli
Inspection Form
Frequent
Inspection
In service for 3 months
or 150 hours, whichever
comes first; or Out of
service for a period of
more than 3 months; or
Purchased used.
Owner, Dealer,
or User
Operation and Maintenance
Manual and applicable Dingli
Inspection Form
Annual
Machine
Inspection
Annually, no later than
13 months from the date
of prior inspection.
Owner, Dealer,
or User
Operation and Maintenance
Manual and applicable Dingli
Inspection Form
Preventative
Maintenance
At intervals as specified
in the Operation &
Maintenance Manual
Owner, Dealer,
or User
Operation and Maintenance
Manual and applicable Dingli
Inspection Form
SINCE THE MACHINE MANUFACTURER HAS NO DIRECT
CONTROL OVER THE FIELD INSPECTION AND MAINTENANCE,
SAFETY IS THE RESPONSIBILITY OF THE OWNER/OPERATOR
.
3.2.2 Preparation for Use
Before a new machine is put into operation it must be carefully inspected for any evidence of
damage resulting from shipment and inspected periodically thereafter, as outlined in Delivery
and Frequent Inspection (see section 3.2.3). During initial start-up and run, the unit should be
Summary of Contents for BA14J-AWD
Page 1: ...Operation Maintenance Manual Table of Contents Dingli Machinery i Series 1 ...
Page 51: ...Operation Maintenance Manual Section4 Machine Controls and Indicators Dingli Machinery 4 17 ...
Page 52: ...Operation Maintenance Manual Section4 Machine Controls and Indicators Dingli Machinery 4 18 ...
Page 53: ...Operation Maintenance Manual Section4 Machine Controls and Indicators Dingli Machinery 4 19 ...
Page 84: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 2 ...
Page 85: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 3 ...
Page 86: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 4 ...
Page 87: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 5 ...
Page 88: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 6 ...
Page 89: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 7 ...
Page 90: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 8 ...
Page 91: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 9 ...
Page 92: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 10 ...
Page 93: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 11 ...
Page 94: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 12 ...
Page 95: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 13 ...
Page 96: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 14 ...
Page 97: ...Operation Maintenance Manual Section8 Schematics Dingli Machinery 8 15 ...