83
Fig. 6-2 Unpacking process
Caution!
When dismantling the enclosures, with respect to the steel-strip
wooden boxes, first bend the steel-strip buckle to the shape shown
in Fig. 6-3 by using pliers or other hardware tools. For the wooden
boxes nailed with wooden nails, first dismantle the upper enclosure
together with the nails, then dismantle the other enclosures, and
protective cotton gloves shall be worn during operation to prevent
scratches.
During unpacking, knocking the wooden boxes roughly is prohibited.
For the dismantling of all the enclosures of the wooden boxes, the
impact on the content shall be avoided.
Fig. 6-3 Steel-strip buckle.
MVF2000 Transportation of MVD cabinet:
After all the packages of the MVD cabinet are dismantled (excluding the pallet), a crane
or a forklift is required to get them out of the wooden pallet.
Use a crane for In-line cabinet
1. Power cell cabinet with control cabinet and Junction cabinet shall be lifted by using
four holes of angle steels on the top of the cabinet as shown in Fig. 6-4. And the
angle steels should be uninstalled after the lifting.
2. Since the weight of the transformer cabinet is heavy, lifting by using the lifting ring on
Dismantle the upper enclosure first;
Dismantle the side enclosures and the
front & rear enclosures;
Dismantle the EPE foam, VCI bag and
the plastic-steel tightening strip;
The dismantled wooden packing boxes
shall be disposed environmentally in
accordance with related requirements.
Side enclosure
Tightening
strip
Motherboard
VCI bag
Upper enclosure
Front enclosure
Summary of Contents for MVF2000 Series