Chapter 5 Installing the IDS-4235 and IDS-4250
Installing the Accessories
5-36
Cisco Intrusion Detection System Appliance and Module Installation and Configuration Guide Version 4.1
78-15597-02
To mark the rack, follow these steps:
Step 1
Place a mark on the rack’s front vertical rails where you want to locate the bottom
of the appliance that you are installing in the two-post rack.
Note
The bottom of each 1-RU space is at the middle of the narrowest metal
area between holes.
Step 2
Place a mark 44 mm (1.75 inches) above the original mark you made.
Note
Each 1 RU (44 mm, or 1.75 inches) of vertical space on a rack with
universal-hole spacing has three holes with center-to-center spacing
between the holes (beginning at the top of a 1-RU space) of 15.9 mm, 15.9
mm, and 12.7 mm (0.625 inches, 0.625 inches, and 0.5 inches).
Installing the Slide Assemblies in the Rack
You can install the slide assemblies in a two-post, open-frame relay rack having
either universal-hole spacing or wide-hole spacing. You can install the 1-RU slide
assemblies in either a flush-mount or center-mount configuration.
This section contains these topics:
•
Center-Mount Installation, page 5-36
•
Flush-Mount Installation, page 5-39
Center-Mount Installation
The two-post rack kit is shipped with brackets configured for center-mount
installation.