Chapter 5 Installing the IDS-4235 and IDS-4250
Installing the Accessories
5-34
Cisco Intrusion Detection System Appliance and Module Installation and Configuration Guide Version 4.1
78-15597-02
Step 4
Slide the appliance in and out of the rack to verify that the cables are routed
correctly and do not bind, stretch, or pinch with the movement of the
cable-management arm.
Step 5
Make any necessary adjustments to ensure that the cable slack is neither too tight
nor too loose, yet keeps the cables in place as the appliance is moved in and out
of the rack.
Step 6
Replace the rack doors.
Note
Refer to the procedures for replacing the rack doors in the documentation
provided with your rack cabinet.
Warning
Because of the size and weight of the rack cabinet doors, never attempt to
remove or install them by yourself.
Two-Post Rack Installation
You can install the two-post rack (part number IDS-RAIL-2=) in a center-mount
or flush-mount configuration. The two-post kit incorporates slide assemblies that
enable the appliance to be pulled out of the rack for servicing.
You must properly secure the two-post, open frame relay rack to the floor, the
ceiling or upper wall, and where applicable, to adjacent racks, using floor and wall
fasteners and bracing specified or approved by the rack manufacturer.
Warning
Do not attempt to install the appliance into a two-post, open-frame relay rack
that has not been securely anchored in place. Damage to the appliance and
injury to yourself and to others may result.
This section contains these topics:
•
Recommended Tools and Supplies, page 5-35
•
Rack Kit Contents, page 5-35
Summary of Contents for IDS-4230-FE - Intrusion Detection Sys Fast Ethernet Sensor
Page 4: ......
Page 450: ...Appendix B Troubleshooting ...