1 Startup
The system power must
come on when the
power of the control PC
is turned on.
Visual check
2
CXDI Software
startup
The system must start
up with no errors.
Visual check
3 Status
lamps
The lamps must provide
the correct indication
that corresponds to the
sensor statuses.
Visual check
5 System
connections
4 Shutdown
The system power must
go off when the power
of the control PC is
turned off.
Visual check
kV
mA
1
X-ray generator
settings
The conditions under
which calibration is
implemented must be
noted.
Visual check
msec
2 Filter
Filter
type
Visual
check
6 Calibration
3
Calibration
processing
“Calibration completed
successfully.”
Visual check
7 Self-diagnosis
1
Self-diagnosis
pass/fail
Tests 1 to 5 must be
passed.
Visual check
TEST1
TEST2
TEST3
TEST4
TEST5
8
Image quality
1
Phantom
exposure
There must be no
artifacts, shading, grid
stripes, etc.
Visual check
9
Transmission test
1
Dcap, 200 times Transmission must be
successful.
Dcap.exe
10
Ping test
1
Ping, 100,000
times
Communication must be
successful.
Pingtest.exe
1
Dirt, dust inside
PC
There must be no dirt or
dust.
Visual check
2
Event logs
Application logs
Watson logs
There must be no errors
(excluding errors which
have been dealt with).
Visual check
3
System logs
OPU3 logs
There must be no errors
(excluding errors which
have been dealt with).
Visual check
4 Touch
panel
There must be no
deviation or other
problems.
Visual check
5 Date,
time
The date and time must
be correct.
Visual check
6
CXDI software
version
- Visual
check
Ver.
11 PC-related
items
7
CCR folder
backup
-
External media,
etc.
12
System exterior
1
Dirt
There must be no dirt.
Visual check
1
Hookup with RIS,
patient data
terminals
It must be possible to
transmit and receive the
data correctly.
Visual check
2
Exposure
information,
patient data in
film server
There must be no errors
in the information or
data.
Visual check
13 Final
checks
3
X-ray generator,
RIS and other
equipment
The equipment must be
the same as before the
inspection work.
Visual check
Summary of Contents for CXDI-55C
Page 23: ...2 Installation 7 2 CXDI System II assembly package Accessories box Power box ...
Page 115: ...2 Installation Manual 99 2 Power Box Mass 3 7 Kg Unit mm Dimension tolerance 1 Scale 1 N ...
Page 161: ...4a Canon Inc PWB 60 X RAY 1 2 SCHEMATIC DIAGRAM Rev 01 ...
Page 162: ...4b Canon Inc PWB 60 X RAY 2 2 SCHEMATIC DIAGRAM Rev 01 ...