2. Installation
- 25 -
5. Adjusting the Alignment
5.1. Overview
Align the center of the sensor unit with the center of the X-ray tube. Be sure that the crossing angle is
perpendicular.
Note
Alignment of the sensor should be performed based on the assumption that the X-ray generator is set
in the correct horizontal and vertical position. If the X-ray generator is displaced to a large extent, the
alignment of the sensor may not compensate the misalignment of the X-ray generator. In this case,
you need to ask the manufacturer of X-ray generator to align the position of the X-ray generator
again.
Note
After installing the imaging unit in the Bucky unit, stand or table, the cross lines on the imaging unit
surface cannot be confirmed by the user. As a result, after adjusting the X-ray tube position, attach
an indicator mark if necessary. For installation facilities where the X-ray tube is moved, be sure
always attach an indicator mark, and perform positioning of the exposure area before taking the
exposure.
Note
If the table type is used, align the sensor unit before mounting a top panel, photo timer and grid.
5.2. Tools (should be prepared by distributors)
Alignment Adjustment Spacer, Mirror (first-face mirror), Tape, Oil-based Marker, Measure, Rope, and
other requirements.
5.3. Adjustment
5.3.1 Stand
(1) Fix the mirror (first-face mirror) at the center of the sensor unit.
(2) Place the stand temporarily in the position to space enough distance for the exposure.
Distance from the tube to the sensor unit should be 180cm.
●
Using a measure or rope, align the horizontal position of the sensor unit to the center of the tube so
that the distance from the tube to the right and left side of the sensor is symmetric.
[Top View]
x
Fix the mirror
Summary of Contents for CXDI-40G COMPACT
Page 24: ...2 Installation 4 2 CXDI SYSTEM III Assembly Packaging Accessories Box Power Box ...
Page 56: ...2 Installation 36 8 3 When Timeout due to RX_REQ not Negating ...
Page 135: ...2 Installation 115 16 2 Power Box Mass 4 2 Kg not including cable Unit mm ...
Page 136: ...2 Installation 116 16 3 Ready Lamp Unit Mass 0 5 Kg Unit mm ...