3-9
Chapter 3: Operation
(2) Data confirmation method when communication with a setup device has been established
■
EPM (electro-pneumatic module) operation confirmation procedure
The operation confirmation procedure for the EPM is shown below.
Step
Procedure
1
Set the input signal from the controller (constant-current supply) to a value that results in
an actual opening position of 50 %.
2
Referring to 4.3.1, “Measured value confirmation,” confirm that the drive signal of the
process variables is 50±25 %.
Caution
•
If the above conditions are not satised, the EPM balance adjustment is o. Conse-
quently, EPM balance adjustment is necessary. If EPM balance adjustment is not
performed appropriately, the valve position may vary suddenly and damage the
EPM, so be sure to have this adjustment carried out by Azbil Corporation service
personnel, or by a representative who has received Azbil Corporation training.
■
Self-diagnostic results confirmation procedure
The procedure for confirming self-diagnostic results is shown below.
Step
Procedure
1
Set the input signal from the controller (constant-current supply) to a value that results in
an actual opening position of 50 %.
2
Referring to 4.8, “Self-diagnostics,” perform the self-diagnostics and confirm that the
diagnostics pass.
If not, refer Chapter 5, “Troubleshooting,” and take the appropriate measures.
Summary of Contents for AVP200
Page 30: ......
Page 66: ...2 28...
Page 80: ...4 4 Menu Tree...
Page 120: ...5 16...
Page 128: ...6 8 For models those date of manufacture are before September 2017...
Page 130: ...6 10 For models those date of manufacture are before September 2017...
Page 132: ...6 12 For models those date of manufacture are before September 2017...
Page 136: ...6 16 For models those date of manufacture are after October 2017...
Page 138: ...6 18 For models those date of manufacture are after October 2017...
Page 184: ...Appendix A Specifications A 25...
Page 185: ......
Page 188: ......
Page 190: ......