FireFinder
™
Installation Commissioning & Operation
Page 90
21.1 Procedure
The following tests are the minimum that shall be performed when commissioning a system using the
FireFinder
™
Fire Alarm Control Panel. Supplements to these test may be added by way of attachments or
notation (
using waterproof ink
) to this documentation. If supplements or tests are added reference to them
shall be made at an appropriate point on this document.
This Commissioning Record is to be completed in conjunction with the -
1.
operator's manual;
2.
installer's statement(s);
3.
'as-installed' drawings; and
4.
detector test records,
The Record provides a complete description of the installed system and its tested performance at the time
of being commissioned.
21.2
System Information
Check relevant box
GENERAL
YES
;
NO
:
NA
(a)
Equipment
: Equipment has been designed and constructed in accordance with the
relevant Standards.
(b)
Installation
: Equipment has been located, installed and interconnected in
accordance with the system documentation
(c)
Compatibility
: All detectors and other devices used in the system are—
(i) listed in the operator’s manual;
(ii) compatible with the relevant parts of CIE, particularly that the permitted number
of detectors and other devices for each circuit is not exceeded;
(iii) installed in an environment for which they are suitable;
(iv) not set to a sensitivity outside that prescribed in the relevant product Standard.
(d)
Alarm zone limitations:
The alarm zone limitations in Clause 2.4 of AS 1670.1 are
not exceeded.
(e)
Primary power source
(i) The primary power source for the system has been provided in accordance with
AS/NZS 3000.
(ii) The isolating switch disconnects all active conductors.
(iii) Five operations of the primary power source switch did not cause an alarm to be
indicated on the system.
(f)
Secondary power source
(i) The secondary power source is of a suitable type and capacity complying with the
requirements of Clause 3.16.2 of AS 1670.1.
(ii) The float voltage, charger type and setting is correct and in accordance with the
battery manufacturer’s recommendation.
(g)
Battery temperature and voltage:
The battery voltage corresponds to that specified
by the battery manufacturer for the temperature measured after 24 h quiescent
operation.