ZXR10 8900 Series Hardware Installation Manual
F
IGURE
39 F
IX
C
ABINET BY
P
RESSURE
P
LATE
1.
Flat Washer
2.
Insulated Tube
3.
Bolt M12×80
4.
Nut M12
5.
Spring Washer
6.
Pressure Plate
7.
Footing
8.
Base
4. Insulation Test
Modify the multimeter to resistance grade. Use the two mea-
suring heads to touch the cabinet earthing point and expansion
bolt. Measure their resistance. Continue the next step if the
circuit is an open circuit. If the result shows that it is not an
open circuit, then the cabinet is not insulated with earth. Ex-
amine the insulated tube. Repeat the last step and insulation
test.
Note:
Insulation test has to be implemented immediately after each
cabinet footing is fixed.
Fix Cabinet by
Locknuts
1. Cabinet Height Regulation
Loosen the four bolts that fasten the truckles, and then re-
move the truckles. Loosen the locknuts of footing. Remove
the footing by rotating the height adjusting nut in the direction
of arrowhead, as shown in
Figure 40
.
46