26
If the installation of the oil-water separator is needed, please contact SUNGROW customer
service or designated partners.
5.5
Fixing the MV Station
If the foundation is constructed as the above plan, the MV Station needs to be hoisted to the
desired location and welded.
If the foundation is not constructed as the above plan, it is necessary to fix the fixing point at
the bottom of the inverter (shown as A below) with the existing operating platform using L
mounting parts.
The steps to fixing the L mounting parts is shown in the following figure.
5.6
Removing the Supporting Plates
Before putting the inverter into operation, remove the support plates of the MV Station,
shown as A in the figure below.
System Manual