24
5.3.3 Recommended Foundation Construction Method
The overall diagram is shown in the following figure.
No.
Name
A
Pea gravel ground
B
Foundation
Constructing the Foundation
It is recommended to construct the foundation as the following solution.
No.
Name
C
MV Station base
Fixing the MV Station
Hoisting the MV Station to the desired location and welded.
After completion, anti-corrosion treatment should be done on the welding position.
5.4
Installing the Drain Valve/Oil-Water Separator
There are two design schemes at the bottom of MV Station. Drain valve or oil-water
separator can be installed according to customized requirements.
For ease of installation, it is recommended to install the drain valve or oil-water
separator before hoisting the MV Station to the installation position.