19
5
Mechanical Installation
Respect all local standards and requirements during mechanical installation.
5.1
Transport
All devices are installed inside the MV Station before delivery. The MV Station should be
transported as a whole. Transport the MV Station by crane with sufficient load capacity.
The MV Station is delivered to the user by a forwarding company. After unloading, the MV
Station will be transported to the installation site by the plant staff.
Local standards and regulations on the container transport and loading &
unloading, especially those safety instructions, should be observed at all times.
•
All the accessory appliances to be used during transport should be maintained
beforehand.
•
The transport of the MV Station must be performed by qualified personnel.
Qualified personnel are those who have been trained, especially in safety
operation.
Keep in mind the dimensions and total weight of the MV Station at all times!
Ensure that the following requirements are met:
•
All the doors are locked.
•
Choose appropriate crane or hoist to transport the MV Station. The crane or hoist must
be sufficient to bear the weight of the MV Station.
•
An additional traction vehicle may be required for uphill/downhill road transport.
•
Anything, which may hinder the transport, like trees, cables (or similar), should be
removed.
•
Transport the MV Station on fine weather days as far as reasonably possible.
•
Warning signs or barriers must be posted near the transport areas to avoid accidental
injuries.
Additionally, the following should be met when the MV Station is placed on the ground: