7.4
Preparation before Starting
•
Place the disassembled protection grills to their original positions and ensure the
connection is secure.
•
Close and lock the cabinet door.
•
Clean the device site. Make sure the position is clean without flammable or explosive
materials.
•
Ensure the ventilation of the installation place.
•
Recheck and ensure whether inverter and switches upstream and downstream can meet
the requirements flexiblely .
7.5
LCD Parameter Setting
When the LCD is on, set the display language, date and time, communication parameters,
active power limitation, etc. according to Chapter
in this manual
and view the running information and perform related operation.
7.6
Completing Commissioning
If all the start-up procedures have been performed, check the operating condition of the MV
Station.
•
Check whether there are anomalies of the module: abnormal noise, overheating,
smoking or unusual odor.
•
Check that the grid-connected voltage, current, and THD of the MV Station are stable.
•
Check the grounding of the MV Station enclosure.
•
Check the functionality of the LCD display.
•
Record accurately the operation data during commissioning.
The duration of commissioning depends on the plant scale, plant location, on-site
environmental conditions and so on. Usually, if the in-site condition is good, the
commissioning can last for 1 week, i.e. 168 hours.
The commissioning of the MV Station is completed. MV Station operates normally.
After successful commissioning, the MV Station will be put into operation.
Local/national standards about the min. electric clearance around the MV Station
should be respected.