Instruction Manual ScrubberGuard
Commissioning
44
14830E/2
6
Commissioning
The initial start-up of the web user interface via the Ethernet interface is described in the
Reference Handbook. If malfunctions occur, consult the Section 10.
The following basic principles apply when operating the ScrubberGuard:
▪
The AquaScat SG acts as master unit for the entire ScrubberGuard system.
▪
The AquaScat SG controls the ScrubberGuard controller and reads the measuring values
from the OilGuard SG and pH probe.
▪
The customer interface is operated from the AquaScat SG.
▪
Parameterization is thus made on the AquaScat SG.
Proceed with the initial start-up in accordance with the following table:
WORKSTEP
ADDITIONAL INFO / IMAGES
1.
Check the screw connections on the entire sys-
tem. Check the water connections, inlet/outlet
connections and pipes.
2.
Ensure that the sample can drain away without
obstructions.
3.
Ensure that the electrical installation is made cor-
rectly, that all covers are attached and that the
door on the ScrubberController is closed.
4.
Open the sample feed to the system.
If the optional inlet pump is integrated,
the supply line must be filled with water before-
hand.
The pump may only be
operated dry for a maximum
of 30 seconds. Danger of
overheating!
5.
To prevent the pumps from running dry, fill the
sample tank with approximately 3 liters of water.
6.
Switch on the system at the main switch.
6.1: The welcome screen appears on the display
of both measuring instruments.
The factory setting language is English. Accord-
ingly, the displayed language during the initial
start-up is English.
6.2: The instruments carry out an internal func-
tional check.