Instruction Manual AquaScat 2 P
Initial start-up
22
11838E/2
6.
Initial start-up
The initial start-up with the web user interface via the Ethernet interface is described in the
Reference Manual.
Proceed with the initial start-up in accordance with the following table. If malfunctions oc-
cur, please refer to Section 9.
WORKSTEP
PROCEDURE
1.
Check the sampling system for
the correct sample feed and
then open the sample feeding.
Section 4.4.1
2.
Check the flow rate.
Section 2.4
3.
Make sure that the photometer
is correctly mounted and that
the electrical connections are
correctly connected.
Section 4.2
4.
Establish service voltage to the
photometer.
4.1: Welcome screen appears.
4.2: The instrument carries out an internal func-
tional check.