ActiveScale™ OS X100 Rackless Installation Guide
131
10.3.1 Summary of workflow
1. Bring a laptop with all data, cables, and certificates listed in
What to bring with you to the data center
2.
Do additional setup for a multi-site deployment
3.
Connect the system to your networks
4.
Run the pre-login configuration wizard (multi-site version)
5.
Run the post-login configuration wizard (multi-site version)
6.
Tip:
Total time estimate: 20-48 hours, depending on the capacity of each rack.
Note:
Systems are sold and factory configured as either single site or multi-site.
Do not attempt to convert a single site system into a multi-site system.
10.3.2 Do additional setup for a multi-site deployment
This step involves connecting additional cabling for uplinks, reconfiguring System Interconnects, checking
data paths, and so on.
10.3.2.1 Obtain cables and transceivers
Obtain or confirm that you have all parts required, as listed in the table below:
• Transceivers listed are shown with a part number you must purchase for each system. Purchase the
part number specified for your chosen uplink mode. Part numbers correspond to upgrade kits.
Cables are customer-supplied and must be
LC to LC multi- mode fiber optic patch cable
(LC multi- mode
50/125mm MMF OM3 or OM4 10Gb laser optimized fiber). These cables must comply with the Ethernet
10GBASE-SR standard. Ensure that, for the cable type chosen, you do not exceed the specified maximum
Содержание ActiveScale X100
Страница 1: ...ActiveScale X100 Rackless Instalation Guide 6 68841 03 Rev A with ActiveScale OS 6 0 2 software...
Страница 28: ...ActiveScale OS X100 Rackless Installation Guide 28...
Страница 34: ...ActiveScale OS X100 Rackless Installation Guide 34...
Страница 36: ...ActiveScale OS X100 Rackless Installation Guide 36 Assemble the remaining Storage Enclosure Basics on page 66...
Страница 59: ...ActiveScale OS X100 Rackless Installation Guide 59 Figure 3 14 Installing the I O module...
Страница 68: ...ActiveScale OS X100 Rackless Installation Guide 68...
Страница 76: ...ActiveScale OS X100 Rackless Installation Guide 76...
Страница 80: ...ActiveScale OS X100 Rackless Installation Guide 80 Figure 5 30 Rail attaching to front vertical rail...
Страница 91: ...ActiveScale OS X100 Rackless Installation Guide 91 Figure 6 36 Cabling Storage Node 4...
Страница 92: ...ActiveScale OS X100 Rackless Installation Guide 92 Figure 6 37 Cabling Storage Node 5...
Страница 94: ...ActiveScale OS X100 Rackless Installation Guide 94 Figure 6 39 Cabling System Node 1...
Страница 95: ...ActiveScale OS X100 Rackless Installation Guide 95 Figure 6 40 Cabling System Node 2...
Страница 98: ...ActiveScale OS X100 Rackless Installation Guide 98...
Страница 108: ...ActiveScale OS X100 Rackless Installation Guide 108...
Страница 110: ...ActiveScale OS X100 Rackless Installation Guide 110...
Страница 127: ...ActiveScale OS X100 Rackless Installation Guide 127 Figure 10 19 Post Login Storage Policy...
Страница 155: ...ActiveScale OS X100 Rackless Installation Guide 155 Figure 10 47 Post Login Durability Policy...
Страница 162: ...ActiveScale OS X100 Rackless Installation Guide 162...
Страница 234: ...ActiveScale OS X100 Rackless Installation Guide 234...
Страница 238: ...ActiveScale OS X100 Rackless Installation Guide 238...
Страница 240: ...ActiveScale OS X100 Rackless Installation Guide 240...
Страница 244: ...ActiveScale OS X100 Rackless Installation Guide 244...
Страница 260: ...ActiveScale OS X100 Rackless Installation Guide 260...
Страница 262: ...ActiveScale OS X100 Rackless Installation Guide 262 Figure 21 20 Components and port identification...
Страница 263: ...ActiveScale OS X100 Rackless Installation Guide 263 Figure 21 21 ActiveScale X100 cable wiring key...
Страница 264: ...ActiveScale OS X100 Rackless Installation Guide 264...