63
8
Control
Mode
8.2
Leakage test
The leakage test checks whether the main gas valves are leak-tight. The supply gas pressure
is used for this purpose. Since the leakage test line (space between the two main valves)
burns empty in the event of a shut-off, this part is normally without pressure when starting (gas
pressure > min. = 0). The ETAMATIC checks this. Main gas 1 is then opened shortly and gas
flows into the test line (gas pressure > min. changes from 0 to 1). This pressure must then
subsist for 30 seconds. The leakage test is then deemed to be completed.
If the leakage test line is not empty at the start (e.g. as a result of a previous fault shut-down),
main gas valve 2 opens first. The leakage test line is vented (into the combustion chamber or
over the roof, depending on the system; for suggested circuit, see Appendix). It is checked,
whether the line remains pressureless for 30 seconds. Otherwise the procedure is, as de-
scribed previously.
The leakage test is performed before ignition.
The pressure monitor for the leakage test line must be connected to "Gas pressure >min" input
(terminal 47). It also monitors the minimum pressure during operation. If another minimum
pressure should to be monitored during operation, the pressure monitor is, to be looped into
the gas safety interlock circuit, for this purpose.
However, the test line must be designed to ensure that the test time of 30 seconds per valve
is sufficient for reliable detection of a 0.1% leak of the fuel gas consumed at maximum com-
bustion heat output, but at least 50 dm
3
/h.
Содержание ETAMATIC
Страница 1: ...Manual ETAMATIC ETAMATIC S CE 0085 AU 0207 Sensors and Systems for Combustion Engineering...
Страница 2: ......
Страница 7: ...6 Table of Contents 9 27 Dimensions and weight 128 9 28 Declaration of Conformity 131...
Страница 65: ...64 8 Control Mode 8 2 1 Leakage test flow chart Fig 8 4 Flow chart leakage test...
Страница 69: ...68 8 Control Mode Switching in standby via LSB module Fig 8 7 Switching in Standby mode via LSB module...
Страница 90: ...89 9 Appendix 9 8 Process Sequence Charts Fig 9 3 Process sequence chart gas with pilot burner...
Страница 91: ...90 9 Appendix Fig 9 4 Process sequence chart oil with pilot burner...
Страница 92: ...91 9 Appendix Fig 9 5 Process sequence chart gas without pilot burner...
Страница 93: ...92 9 Appendix Fig 9 6 Process sequence chart oil without pilot burner...
Страница 98: ...97 9 Appendix 9 9 Connection Diagrams Fig 9 7 ETAMATIC wiring diagram with ignition flame monitoring...
Страница 99: ...98 9 Appendix Fig 9 8 ETAMATIC S wiring diagram with ignition flame monitoring...
Страница 104: ...103 9 Appendix Fig 9 16 LSB connection ETAMATIC LT1 other LAMTEC devices...
Страница 134: ...133 9 Appendix...
Страница 135: ......