7
Move the wash rack up and down for 1 minute, breaking the surface of the PB1 with gentle, slow
agitation.
8
Move the wash rack to Wash 2 containing clean PB1, making sure that the BeadChips are submerged.
9
Move the wash rack up and down for 1 minute, breaking the surface of the PB1 with gentle, slow
agitation.
10 Remove the BeadChips from the wash rack and inspect them for remaining residue.
If you see residue, submerge the BeadChip in PB1 and carefully use a pipette tip to remove the
remaining residue.
Assemble Flow-Through Chambers
1
Confirm that you are using the correct Infinium glass back plates and spacers before proceeding.
2
Fill the BeadChip alignment fixture with 150 ml PB1 for up to 8 BeadChips.
3
For each BeadChip, place one black frame into the BeadChip alignment fixture.
For example, if you are processing four BeadChips, place four black frames into the fixture.
4
Place each BeadChip into a black frame, aligning the barcode with the alignment fixture ridges. Fully
submerge each BeadChip.