Overview of Server Installation
Cabling the Server
After the cable management arm is installed, cable the server by following these
procedures:
1.
Plug all external cables into the server.
2.
If you installed a switchbox into the rack, route the CPU-to-switchbox cables to
the switchbox.
3.
Bundle all of the cables, including the power cable, then secure them to the cable
management arm using the Velcro strips.
Figure 2-18: Routing and securing the cables
4.
Extend the bundled cables down the rack cable channel.
HP ProLiant ML350 Generation 3 Server Setup and Installation Guide
2-27
HP CONFIDENTIAL
Writer: Richard O. Heath File Name: c-ch2 Overview of Server Installation.doc
Codename: Steel Venom Part Number: 316354-001 Last Saved On: 12/6/02 2:56 PM