Procedure
In the following example, project planning with air filter type LF-AD-1 and
four aspiration apertures, without any other accessories, should comply with
class B. The red arrows show the possible project planning for different pipe
shapes.
Action step
Actions
1
Selection
Selection of the corresponding project planning table based on the air filter
to be used (see chapter "Detailed pipe accessories")
Result
The project planning table is determined
2
Selection
Selection of the number of aspiration apertures in the project planning
table
Result
The achievable sensitivity class for the selected number of aspiration
apertures is determined
3
Selection
Determine the necessary sensitivity to attain the fire sensitivity class
Result
Detection unit and sensitivity setting are determined
4
Selection
Selection of further pipe components (e.g. condensate separator) based on
the components described in the chapter "Pipe accessories"
Result
Pipe project planning table is determined
5
Selection
Pipe length selection
Result
Pipe shape and the necessary fan voltage are determined
Table 17:
Procedure for project planning