Rack and pinion hoist
Assembly and Operating Manual
20 / 92
BL054 GB Edition 08.2015
3.2
Checks before initial commissioning
Checks at the factory
The following tests have already been carried out at the factory:
−
Dynamic test with 1.1x useful load.
−
Electrical tests according to EN 60204
−
Function tests.
3.3
Checks after assembly / daily before starting operation
To ensure safety when handling the machine, the custodian / person
determined by the operating company must carry out a daily check of
certain areas of the machine / parts.
Defects detected must be immediately reported to the supervisor and
rectified. Defects may only be rectified by trained personnel responsible
for maintenance and servicing.
Always carry out visual inspections before function checks. Operation is
prohibited until the defects are rectified.
The following points must be checked daily
−
Visual inspections before start of work
→
refer to Chapter “Operation” in the operating manual
−
Clean the cable bin (keep free from snow and ice in winter).
−
Keep the work area around the machine clear and clean.
For inspections after each installation
→
refer to Chapter 6.5
3.4
Recurring inspections:
Recurring inspections must be carried out in accordance with national
regulations.
GEDA recommends that you carry out a recurring check on an
annual basis. In the case of increased use and strain (e.g. multi-
shift operation) carry out inspections at shorter intervals.
Содержание 14830
Страница 1: ...Original assembly and operating manual Assembly and Operating Manual Rack and pinion hoist For loads...
Страница 2: ......
Страница 3: ...Rack and pinion hoist Assembly and Operating Manual 3 92 BL054 GB Edition 08 2015...
Страница 4: ...Rack and pinion hoist Assembly and Operating Manual 4 92 BL054 GB Edition 08 2015...
Страница 36: ...Rack and pinion hoist Assembly and Operating Manual 36 92 BL054 GB Edition 08 2015...
Страница 90: ...Rack and pinion hoist Assembly and Operating Manual 90 92 BL054 GB Edition 08 2015...
Страница 91: ......