Rack and pinion hoist
Assembly and Operating Manual
43 / 92
BL054 GB Edition 08.2015
4.6.3
Mains connection
A building site main cabinet (according to IEC 60439-4:2004) with fuse
protection of the supply point with min. fusing of 16A slow-to-blow is
required on site.
500 Z with 230 V drive
−
Supply point: 230V/50Hz
−
Fuse protection:
16 A, slow-to-blow
−
Connect the mains supply line (3 m) for the hoist to the building site
main cabinet.
−
A rubber hose line measuring a minimum of
3 x 2.5 mm
2
is required
for extending the mains supply line (see accessories) to avoid
voltage drop and therefore any loss in motor performance. For supply
lines
more than 50 m
long, a cable of minimum
3 x 4 mm
2
should be
used.
If the power supply is poor, unplug any other current consumers.
500 Z with 400 V drive
−
Supply point: 400 V/50Hz
−
Fuse protection:
3 x 16 A slow-to-blow
−
Connect mains supply line (3 m) for the hoist to the building site main
cabinet (plug CEE 5x16 A, 6h, red with phase inverter).
−
A rubber hose line measuring a minimum of
5 x 2.5 mm
2
is required
for extending the mains supply line (see accessories) to avoid
voltage drop and therefore any loss in motor performance.
The green control light on the switch box with main switch
illuminates when the main switch is set to position “1 ” and the
phase position is correct.
Содержание 14830
Страница 1: ...Original assembly and operating manual Assembly and Operating Manual Rack and pinion hoist For loads...
Страница 2: ......
Страница 3: ...Rack and pinion hoist Assembly and Operating Manual 3 92 BL054 GB Edition 08 2015...
Страница 4: ...Rack and pinion hoist Assembly and Operating Manual 4 92 BL054 GB Edition 08 2015...
Страница 36: ...Rack and pinion hoist Assembly and Operating Manual 36 92 BL054 GB Edition 08 2015...
Страница 90: ...Rack and pinion hoist Assembly and Operating Manual 90 92 BL054 GB Edition 08 2015...
Страница 91: ......