7 COMMANDS AND TARGETS
7.1 COMMANDS
7
7.1.5 RELAY MAINTENANCE
PATH: COMMANDS
RELAY MAINTENANCE
This menu contains commands for relay maintenance purposes. Commands for the lamp test and order code are activated
by changing a command setting to “Yes” and pressing the ENTER key. The command setting will then automatically revert
to “No”. The service command is activated by entering a numerical code and pressing the ENTER key.
The
PERFORM LAMPTEST
command turns on all faceplate LEDs and display pixels for a short duration. The
UPDATE
ORDER CODE
command causes the relay to scan the backplane for the hardware modules and update the order code to
match. If an update occurs, the following message is shown.
There is no impact if there have been no changes to the hardware modules. When an update does not occur, the
ORDER
CODE NOT UPDATED
message will be shown.
The
SERVICE COMMAND
is used to perform specific L90 service actions. Presently, there is only one service action available.
Code “101” is used to clear factory diagnostic information stored in the non-volatile memory. If a code other than “101” is
entered, the command will be ignored and no actions will be taken. Various self-checking diagnostics are performed in the
background while the L90 is running, and diagnostic information is stored on the non-volatile memory from time to time
based on the self-checking result. Although the diagnostic information is cleared before the L90 is shipped from the factory,
the user may want to clear the diagnostic information for themselves under certain circumstances. For example, it may be
desirable to clear diagnostic information after replacement of hardware. Once the diagnostic information is cleared, all self-
checking variables are reset to their initial state and diagnostics will restart from scratch.
The
REBOOT RELAY COMMAND
reboots the relay so that changes to configuration settings can take effect. In most cases, if
changes are made to the configuration settings these changes do not take effect unless the relay is rebooted.
With the CyberSentry option, the Administrator or Operator role can initiate the Reboot Relay command.
7.1.6 PHASOR MEASUREMENT UNIT ONE-SHOT
PATH: COMMANDS
PMU ONE-SHOT
This feature allows pre-scheduling a PMU measurement at a specific point in time. This functionality can be used to test for
accuracy of the PMU, and for manual collection of synchronized measurements through the system, as explained below.
When enabled, the function continuously compares the present time with the pre-set
PMU ONE-SHOT TIME
. When the two
times match, the function compares the present sequence number of the measured synchrophasors with the pre-set
PMU
ONE-SHOT SEQUENCE NUMBER
. When the two numbers match, the function freezes the synchrophasor actual values and
the corresponding protocol data items for 30 seconds. This allows manual read-out of the synchrophasor values for the pre-
COMMANDS
RELAY MAINTENANCE
PERFORM LAMPTEST?
No
Range: No, Yes
UPDATE ORDER CODE?
No
Range: No, Yes
REBOOT RELAY?
No
Range: No, Yes
SERVICE COMMAND:
0
Range: 0, 101
UPDATING...
PLEASE WAIT
COMMANDS
PMU ONE-SHOT
PMU ONE-SHOT
FUNCTION: Disabled
Range: Enabled, Disabled
PMU ONE-SHOT
SEQUENCE NUMBER: 0
Range: 0 to nominal frequency – 1 in steps of 1
PMU ONE-SHOT TIME:
2005/06/14 7:58:35
Range: 24h time format
NOTE
Содержание UR Series L90
Страница 14: ...xiv L90 Line Current Differential System GE Multilin 0 1 BATTERY DISPOSAL 0 BATTERY DISPOSAL 0 ...
Страница 68: ...2 34 L90 Line Current Differential System GE Multilin 2 4 SPECIFICATIONS 2 PRODUCT DESCRIPTION 2 ...
Страница 138: ...4 30 L90 Line Current Differential System GE Multilin 4 3 FACEPLATE INTERFACE 4 HUMAN INTERFACES 4 ...
Страница 604: ...9 58 L90 Line Current Differential System GE Multilin 9 6 FAULT LOCATOR 9 THEORY OF OPERATION 9 ...
Страница 652: ...A 16 L90 Line Current Differential System GE Multilin A 1 PARAMETER LISTS APPENDIX A A ...
Страница 772: ...B 120 L90 Line Current Differential System GE Multilin B 4 MEMORY MAPPING APPENDIX B B ...
Страница 802: ...C 30 L90 Line Current Differential System GE Multilin C 7 LOGICAL NODES APPENDIX C C ...
Страница 812: ...D 10 L90 Line Current Differential System GE Multilin D 1 IEC 60870 5 104 APPENDIX D D ...
Страница 824: ...E 12 L90 Line Current Differential System GE Multilin E 2 DNP POINT LISTS APPENDIX E E ...
Страница 834: ...F 10 L90 Line Current Differential System GE Multilin F 3 WARRANTY APPENDIX F F ...
Страница 846: ...xii L90 Line Current Differential System GE Multilin INDEX ...