General System Requirements
1.3 Delivery Requirements
1.3.3 Conveyance of Crated System Components Within the Site
Discovery NM/CT 670 – Standard Integration Instructions
5483063-1EN, Rev.2, ©2015 GE Healthcare
1-8
1.3.3 Conveyance of Crated System Components Within the Site
Regardless of whether the system is being delivered from the unloading area to storage, from the
unloading area to unpacking area for installation or from storage to the installation area, take care
to adhere to the following guidelines:
Ensure that there is a free path, including an elevator if necessary, to wheel the components
to the installation area.
Verify that the route selected has sufficient clearance and load carrying capacity (see
Table 1-2, D670 Additional CT-specific Components and Clearance — Metric, p.1-12
Table 1-4, D670 Additional CT-specific Components and Clearance — Imperial, p.1-15
and
Table 1-1, D670 Components and Clearance — Metric, p.1-10
and Clearance — Imperial, p.1-13
).
The subsystems may be lifted only with a forklift and only when attached to their original
shipping pallets.
If the outer crating is removed after delivery, do not detach the subsystems from their original
shipping pallets before they are conveyed to the scan room for installation.
CAUTION
!
Lifting of the gantry without its original shipping pallet or using a crane may damage the system and is
prohibited.