General System Requirements
1.3 Delivery Requirements
1.3.2 Delivery Unloading Area and Equipment
Discovery NM/CT 670 – Standard Integration Instructions
5483063-1EN, Rev.2, ©2015 GE Healthcare
1-7
1.3.2 Delivery Unloading Area and Equipment
The minimal unload area adjacent to the delivery truck is 15m
×
15m (50'
×
50'). Make sure that
the unloading and storage areas are large enough to maneuver a forklift with crates.
It is recommended that the delivery site is selected to provide the shortest and smoothest
route for component conveyance:
If delivered on the installation day, as close as possible to the scan room for installation
If delivered prior to the installation day, as close as possible to the storage area
If a forklift is required in order to unload or move system components:
Allocate a forklift that is capable of lifting more than the maximum weight of the heaviest
unit (see
Table 1-1, D670 Components and Clearance — Metric, p.1-10
Components and Clearance — Imperial, p.1-13Table 1-2, D670 Additional CT-specific
Components and Clearance — Metric, p.1-12
Table 1-4, D670 Additional CT-specific
Components and Clearance — Imperial, p.1-15
Take into account sufficient floor space to maneuver the forklift near the delivery truck.