9.1.
Tests on Battery Lines
Image 11.2 shows the general setup for tests for
which connector interruption tests must be
performed.
The PFM 200N100.1, especially when large
currents are involved, provides the best safety for
the user.
Image 9.2: Test Setup for Battery Lines
9.2.
Tests on Data Lines
Image 11.3 shows an application whereby up to
16 data or signal lines may be interrupted
simultaneously.
Image 9.3: Test Setup for Battery Lines
9.2.1. Tests on Data Lines with the AutoWave.control Software
Select from the Standard Library the path
-
Open / Automotive / OEM / LV 124 / (2013-02) / 12V System / E-14 Connector Interruption
-
Select
“E-14 Connector Interruption Data”
from the list
-
Choose
Select
to open the file
Checking the Settings
-
Parameter for the Dropout Test (1)
t1
: 10s interruption time
t2
: 1s switch on before the next
interruption
t3
: 1 Cycle
-
Switch Selection (2
):
Shows that all data lines S1 to S16
together in the 2
nd
sequence will be
opened. Switches that are not connected
will also switch.
-
Choose
Start
to start the test
Figure 9.4: Test Window for E-14 Test Case 3