EM TEST (Switzerland) GmbH
PFM 200N100.1
User’s Guide
Ver. 1.12
30 / 43
Test Setup
Figure 9.3 shows the application of dropout
simulations on signal and data lines up to 2 A,
where up to 16 lines individually or simultaneously
may be interrupted. The return lines of each pair
can be individually tested.
For higher current, like with T.31 (battery minus)
one may use S1N.
Figure 8.3: Pin Interruptions on Data Lines
8.1.
Test Case 1 Slow Interval
Each pin must be disconnected for
10 s
and then
reconnected (slow interval).
One could also perform this test manually with a
switch. However, use of the PFM 200N100.1
offers the capability of exactly 10 s, down to ms
accuracy, thus resulting in repeatable results.
Figure 8.4: Test Pulse Test Case 1
8.1.1. Tests of Data Lines with the AutoWave.control Software
Select from the Standard Library the path
-
Open / Automotive / OEM / LV 124 / (2013-02) / 12V System / E-13 Pin Interruption
-
Select
“Test Case 1”
from the list
-
Choose
Select
to open the file
Checking the Settings
-
Selecting the Number of Data Lines
Deselect the check box
(1)
for each
sequence that is not necessary. (For
example, the DUT has only 4 data lines)
-
Parameter for Cycles (3)
3 cycles for sequences 1 to 4
-
Parameter for the Dropout Test (3)
t1
:
10s interruptions,
t2
:
Should be long enough that the DUT
and periphery has reached 100%
operability.
t3
:
1 cycle per test run
-
Switch Selection
: Shows which data lines
are active for the selected sequence
(3)
-
If a parameter is modified,
< Modified
Standard >
at the top edge of the screen
(4)
-
Save
the test if it is to be used again at a
later time.
-
Choose
Start
to start the test
Figure 8.5: Test Window for E-13 Test Case 1 Showing a Modified
Test