5
Boiler block assembly
Logano G225/Logano plus GB225 - We reserve the right to make any changes due to technical modifications.
28
5.3
Installation of pre-assembled boiler
heat exchanger
Pre-assembled boiler blocks are leak tested in the factory
prior to delivery.
V
Cut through the securing straps [1].
V
Remove the pallet prior to positioning the boiler block.
Fig. 28 Boiler block on a pallet (as delivered condition)
1
Securing straps
5.4
Assembly steps for boilers supplied in sections and as ready assembled block
Carry out the steps detailed in this chapter for deliveries
in sections or as block. Any assembly discrepancies
between the sectional and block delivery are highlighted
in this text.
5.4.1
Fitting the adjustable feet
You can level the boiler using the adjustable feet (for
packing details see package contents) to prevent air
pockets forming inside the boiler.
V
Tip the boiler or support it on a square timber.
V
Insert adjustable feet 5 – 10 mm.
V
Gently set the boiler down.
Fig. 29 Fitting the adjustable feet
5.4.2
Inserting the hot gas baffle plates
V
Remove the corrugated cardboard packaging when
the block is supplied ready assembled.
V
If the boiler is supplied in sections, remove the hot gas
baffles from the box containing the loose fittings.
V
Insert the hot gas baffles into the centre 2nd hot gas
flues as indicated in the table below. The cast lugs
should point towards the centre of the boiler.
Fig. 30 Inserting hot gas baffles into 2nd hot gas flue
(in this case in the centre)
Danger: Risk of fatal injury from falling
objects.
V
Ensure that there is a suitable means of
supporting the load.
V
Observe all locally applicable health &
safety regulations regarding lifting
equipment.
6 720 615 876-28.1RS
1
6 720 615 876-29.1RS
6 720 615 876-30.1RS