Installing the burner hood
V
Locate the burner hood on the hooks on the boiler
outer casing.
V
Secure the burner hood with screws.
Fig. 69 Installing the burner hood
7.7
Setting the room controller/control
unit
V
Check/make following settings on the room controller:
– Automatic operating mode
– Required room temperature
– Required DHW temperature
– Required heating program
Fig. 70 Room controller
After completion of the commissioning steps
V
Set both rotary selectors on the control unit to "AUT"
(automatic mode). In this setting, the room controller
takes over control.
Fig. 71 Setting the control unit
Danger: Risk of fatality from electric shock.
V
Only operate the boiler with the burner
hood fitted.
6 720 615 876-68.1RS
For further information about operating the
system, e.g. setting the temperatures, refer to
the room controller documentation.