112
Current protection
Chapter 11
Verifying settings by secondary
injection
6.7.6
Verifying instantaneous back-up trip at “CB faulty” condition
Applies in a case where signal “CB faulty and unable to trip” is connected to input CBFLT.
Procedure
1.
Repeat the check of back-up trip time. Disconnect current and start
input signals.
2.
Activate the input CBFLT. The output CBALARM (CB faulty alarm)
should appear after set time tCBAlarm. Keep the input activated.
3.
Apply the fault condition, including start of BFP, with current above
set current value.
4.
Verify that back-up trip is obtained without intentional delay, e.g.
within 20 ms from application of start.
5.
Disconnect injected AC and input signals.
6.7.7
Verifying the case FunctionMode = Contact
It is assumed that re-trip without current check is selected,
RetripMode = No I>
check.
Procedure
1.
Set FunctionMode = Contact
2.
Apply input signal for CB closed to relevant input or inputs CBCLDL*
3.
Apply input signal, or signals for start of BFP. The value of current
could be low.
4.
Verify that re-trip and back-up trip are achieved after set times.
5.
Disconnect the start signal(s). Keep the CB closed signal(s).
6.
Apply input signal(s), for start of BFP. The value of current could be
low.
7.
Arrange disconnection of CB closed signal(s) well before set
back-up trip time t2.
8.
Verify that back-up trip is not achieved.
9.
Disconnect injected AC and start input signals.
6.7.8
Verifying the function mode “Curr&Cont Check”
To be made only when
FunctionMode = Curr and Cont
is selected. It is suggested to make the
tests in one phase only, or at three-phase trip applications for just three-phase tripping.
Checking the case with fault current above set value IP>
The operation shall be as in
FunctionMode = Current.
Procedure
1.
Set FunctionMode = Curr&Cont Check
2.
Leave the inputs for CB close inactivated. These signals should not
influence.
Содержание RELION REL670
Страница 8: ...Contents ...
Страница 54: ...46 Checking the optical connections Chapter 6 Checking the external optical and electrical connections ...
Страница 72: ...64 About this chapter Chapter 9 Establishing connection and verifying the LON communication ...
Страница 78: ...70 Downloading settings and configuration from a PC Chapter 10 Configuring the IED and changing settings ...
Страница 174: ...166 Remote communication Chapter 11 Verifying settings by secondary injection ...
Страница 190: ...182 Maintenance Chapter 13 Fault tracing and repair ...
Страница 198: ...190 Glossary Chapter 14 Glossary ...