Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022 Page
87
of
146
5.11.
Unpack the Charge Pole
5.11.1. Before
unpacking
The Charge Pole is delivered on trailer.
NOTICE
Unloading Charge control set
The delivery truck only unloads the Charge Pole and pallet carrying the
parts of the Charge Pole.
The delivery truck will not move the Charge Pole set to its final location.
The placement of the Charge Pole to its final location is the responsibility
of the contractor. Upon request it is possible to order a truck with a crane.
CAUTION
Do not pollute the environment with plastic and cardboard packing.
Depollute these things according the regional applicable regulations as
well as environment-friendly.
Preconditions:
All construction work is completed.
The product is delivered by a transport company at the confirmed date of delivery.
Equipment to set the pole in the right position during installation (in all directions).
Crane to lift the frame of the pole. The minimum load is about 3761 lb and minimum
height required about 23 ft.
Mobile elevated work platform to tighten the bolts between horizontal and vertical
frame, plate work installation and adjustment of the Pantograph. Required height about
19.69 ft.
1. Check the delivery goods and boxes for damages.
2. Check that all cable connections on the pantograph and Wi-Fi communication unit are
tight.
WARNING
Make sure that the painted seal on the pantograph
electrical connectors are not damaged. Is this not the
case, contact ABB Delivery department (see
Contact
information
on Page 14 for contact details).