DANGER
Make sure that the main switch of the power supply group for the product
is set to the OFF position. Do a voltage check to make sure that the
electrical power is disconnected from the system. Secure against
resetting.
WARNING
Make sure that personnel cannot be crushed or become trapped while
moving the Power Cabinet.
CAUTION
Warranty
Damage due to moving the Power Cabinet to its position is not covered
by the warranty.
CAUTION
Do not use a compressor to clean the Power Cabinet. Use a vacuum
cleaner.
1. Use one of the two options to move the Power Cabinet to the foundation.
2. When the Power Cabinet is about 19.69 Inch above its location, continue the installation
procedure with
Install Power Cabinet onto the foundation
on Page 60.
5.4.1. Move cabinet with a hoist
A Swivel eye bolts (standard delivered with the cabinet)
B Lifting loops
C Hoisting equipment
Preconditions:
A minimum of two persons is required: one person to operate the hoisting equipment,
the other person to guide the Power Cabinet to its location.
Use M16 swivel eye bolts (A) or M16 bolts with lifting loops (B).